1. By three rulings adopted on 28 July 2020, the Court of Appeals (Cour d’appel) of Paris confirmed the interim orders issued by the Presiding Judge of the Commercial Court (Tribunal de commerce) of Paris. These interim orders imposed on Electricité de France (hereinafter “EDF”) to suspend the performance of the framework agreements for the supply of power executed in application of the regulated access to historic nuclear electricity mechanism (hereinafter the “ARENH“) due to the fulfillment of the conditions for the application of force majeure defined in these agreements.
2. In our article of 25 May 2020, we presented the ARENH mechanism and the interim order of the Commercial Court of Paris of 20 May 2020 between EDF and Total Direct Energie, which is the subject of one of the three rulings of 28 July 2020 of the Court of Paris. Three other interim orders were adopted on the following 26 and 27 May between EDF, on the one hand, and Gazel Energie Génération, Gazel Energie Solutions and Alpiq Energie France, on the other hand, relating to the same question and taking up the solution developed in the order of 20 May 2020. All these four interim orders were appealed by EDF.
3. With its three ruling of 28 July 2020, the Court of Appeals of Paris confirmed in full the three interim orders issued between EDF, on the one hand, and Total Direct Energie, Gazel Energie Génération and Gazel Energie Solutions, on the other hand. Like the Commercial Court of Paris, it considered that the conditions for the application of force majeure provided for by the ARENH supply framework agreements were in these cases clearly met and consequently that EDF’s refusal to apply this clause blatantly called into question the principle of the binding force of contracts as well as the one prohibiting self-justice and therefore resulted in a clearly unlawful disorder.
4. To date, no information is available as to whether or not EDF intends to appeal the rulings of the Court of Appeals of Paris before the French Judicial Supreme Court (Cour de cassation) in these cases.
5. The Court of Appeals of Paris adopted a fourth ruling on 28 July 2020 relating to the interim order between EDF and Alpiq Energie France. This ruling was limited to acknowledging EDF’s withdrawal and its acceptance by the respondent.
6. Finally, the French Electricity Regulatory Commission (Commission de regulation de l’électricité), which drafted the standard model used for the preparation of the framework agreements concluded between EDF and power purchasers under the ARENH, initiated on 31 July 2020 and until 15 September a public consultation. This public consultation intends to improve the drafting of the force majeure clause to take account of the solution adopted by the Court of Appeals of Paris.
- Adoption of the French Decree extending by one year the application of the French special COVID-19 foreign investment control provisions - January 11, 2021
- French veto to the acquisition of Photonis par Teledyne - December 23, 2020
- One-year extension of the French special COVID-19 foreign investment control provisions - December 21, 2020
- Strengthening the control of the European Commission on “killer acquisitions” - October 2, 2020
- The European Court of Justice upheld the support schemes of the Member States of the European Union for cogeneration units being or not high-efficiency facilities - September 24, 2020
- #COVID-19 : Confirmation by the Court of Appeals of Paris of the orders imposing on EDF to suspend the performance of the contracts for the sale of ARENH power due to force majeure - August 24, 2020
- #COVID-19 : Adoption of the temporary reduction from 25% to 10% of the capital holding threshold, triggering the control of foreign investments - July 29, 2020
- Draft Guidelines on agreements allowing to achieving sustainable objectives of the Dutch competition authority - July 15, 2020
- #COVID-19 : Regulated Access to Historic Nuclear Electricity and Force Majeure - May 26, 2020
- War of courts at the top of the European Union: The ruling of the German Federal Constitutional Court in Karlsruhe - May 12, 2020